SA LA GARONNE mobile units at work in the city centre

Expertise 03 / Trenchless

Trenchless rehabilitation

Renovating existing networks from the inside: CIPP lining, sleeving, milling and robotic operations. Less road opening, shorter schedules, limited disruption.

Share of business 10% of businessProcesses CIPP lining · sleeving · millingRobotics RIC 4K 360° · patented 2018Qualification FNTP 5221 · man-entry networksRoadway Not opened

Our approach

A new pipe inside the old one. Without opening the street.

Renewing a buried network by open trench means opening the road, diverting traffic and immobilising a neighbourhood for weeks. Trenchless rehabilitation offers an alternative: renovating the pipe from the inside, working from the existing manholes.

SA LA GARONNE has made these techniques a distinctive part of its know-how. Continuous CIPP lining, sleeving, robotic milling, spot repairs: our crews and mobile units work on live networks, in the dense city centre as well as in outlying areas.

The result: a structurally new pipe, a service life extended by several decades, a shorter worksite and a road left intact.

The process, step by step

Rehabilitation without opening the road.

Trenchless rehabilitation renovates existing networks from the inside. Less road opening, shorter schedules, less disruption for residents.

01
CCTV inspectionPrecise assessment of the pipe's condition before any work begins.
02
Robotic preparationHigh-pressure jetting, milling of obstructions and deposits, preparation of service connections.
03
CIPP lining / sleevingInstallation of a cured-in-place liner: a new pipe inside the old one.
04
Return to serviceService connections reopened, checks completed, flow restored. The street was never opened.

Discover trenchless rehabilitation

Schematic street cross-section: trenchless rehabilitation of a buried pipe Mobile unit · trenchless Manhole 0 m −3 m −6 m Existing pipe · Ø 800 mm CCTV inspection Network in service
Scroll to run the operation

Techniques

The processes we deploy.

Every network is different: the survey determines the technique best suited to the pipe's condition and the site constraints.

01
CCTV inspection and survey

Camera survey — including the RIC, La Garonne's patented 4K 360° inspection robot — recording defects and measuring ovalisation and adverse gradients.

02
High-pressure jetting and preparation

High-pressure cleaning of the pipe, removal of deposits, surface preparation before lining.

03
Robotic milling

Removal of obstructions (roots, encrustation, intruding connections) by a milling robot operated from the surface.

04
Continuous CIPP lining

A resin-impregnated liner, installed and cured in place: a new, continuous and watertight pipe inside the existing one.

05
Partial lining and sleeves

Localised repair of a section or joint using a sleeve or short liner, without treating the whole length.

06
Reopening of service connections

Robotic reopening of service connections after lining, reworking of joints and tightness testing.

Benefits

What the city gains.

  • Road left intactNo trench along the route: the road, the pavements and the neighbouring utilities stay intact.
  • Shorter schedulesOperations measured in days or weeks, where an open trench would be measured in months.
  • Limited disruptionLess noise, dust and traffic diversion for residents, businesses and road users.
  • SustainabilityA structurally reinforced, watertight pipe, good for several more decades of service.
  • Controlled overall costLess excavation, backfilling and reinstatement: an optimised budget for the local authority.

Scope of work

Networks of every size, in every setting.

Sewer mains, service connections, structures: we match the technique to the diameter, the material and the condition of the pipe.

Live networksDense city centreMan-entry sewersNon man-entry pipesService connectionsManholes and structuresRobotic operations

Technical data

SurveyCCTV inspection · RIC 4K 360° robot
Networks inspectedover 120 km in Toulouse
ProcessesCIPP lining · sleeving · sleeves
PreparationHigh-pressure jetting · robotic milling
FNTP qualification5221 · rehabilitation of man-entry networks
RoadwayNot opened along the route
Area of operationToulouse Métropole & surrounding area

Contact

A network to build, maintain or rehabilitate?

Let's talk about your project. Our teams give you precise answers, drawing on 70 years of worksites.